8. Defect Tracking & Reporting

8.1 Defect Classification

Severity Levels:

LevelDescriptionExample
S0 - BlockerSystem unusableLogin broken, data loss
S1 - CriticalMajor feature brokenPDF generation fails
S2 - MajorFeature impairedFilter not working
S3 - MinorMinor issueUI misalignment
S4 - TrivialCosmeticTypo

Priority Levels:

LevelDescriptionResolution SLA
P0 - CriticalMust fix immediately4 hours
P1 - HighFix in current sprint2 days
P2 - MediumFix in next sprint1 week
P3 - LowFix when convenientBacklog

8.2 Defect Lifecycle

New → Assigned → In Progress → Resolved → Verified → Closed
                      ↓                       ↓
                   Reopened ←─────────────────┘

8.3 Defect Tracking

Tool: GitHub Issues

Labels:

  • bug - Identifies as defect
  • severity:S0 to severity:S4
  • priority:P0 to priority:P3
  • module:upload, module:reports, etc.
  • regression - Regression from previous release

8.4 Escalation Path

SituationEscalate ToTimeframe
P0/S0 not acknowledgedDev Lead1 hour
P0/S0 not resolvedProject Manager4 hours
P1 not acknowledgedDev Lead1 day
Repeated regressionsDev Lead + QA LeadImmediate

10. Test Deliverables

10.1 Documents

DocumentDescriptionOwner
Test PlanThis document suiteQA Lead
Test CasesDetailed test specificationsQA Engineers
RTMRequirements traceabilityQA Lead
Test Summary ReportExecution resultsQA Lead
Defect ReportIssue trackingQA Engineers

10.2 Test Summary Report Contents

  • Test execution summary
  • Pass/fail metrics
  • Coverage analysis
  • Defect summary
  • Recommendations
  • Sign-off

11. Test Schedule & Milestones

11.1 Phase Timeline

PhaseDurationKey Activities
Development TestingContinuousUnit tests, integration tests
Validation Testing2 weeksSystem testing, performance
Implementation Testing1 weekUAT, regression
Operational Testing2 daysProduction validation

11.2 Milestones

MilestoneCriteria
VRR CompleteUnit coverage ≥85%, no P0 defects
IRR CompleteValidation passed, security tested
UAT CompleteStakeholder sign-off
ORR CompleteProduction ready

12. Test Roles & Responsibilities

12.1 Team Structure

         Project Manager

    ┌──────────┼──────────┐
    │          │          │
 QA Lead    Dev Lead    DevOps
    │          │
 QA Eng    Developers

12.2 Role Definitions

QA Lead:

  • Develop test plan
  • Coordinate testing activities
  • Report metrics
  • Make go/no-go recommendations

QA Engineer:

  • Execute test cases
  • Develop automated tests
  • Log defects
  • Verify fixes

Developer:

  • Write unit tests (≥85% coverage)
  • Fix defects
  • Participate in code reviews

DevOps:

  • Maintain test environments
  • Configure CI/CD pipelines
  • Support deployment testing

13. Test Metrics & Reporting

13.1 Key Metrics

MetricFormulaTarget
Test Coverage(Executed / Total) × 100≥95%
Pass Rate(Passed / Executed) × 100≥98%
Defect DensityDefects / KLOC<5
Defect Removal Efficiency(Pre-release / Total) × 100≥95%

13.2 Reporting Frequency

ReportAudienceFrequency
Daily StatusDev teamDaily
Sprint ReportStakeholdersSprint end
Release ReportExecutivesRelease

14. Communication Plan

14.1 Meetings

MeetingParticipantsFrequencyPurpose
Daily StandupDev + QADailyStatus sync
Defect TriageQA + DevDailyPrioritize defects
Sprint ReviewAllBi-weeklyDemo + feedback
UAT SessionQA + UsersWeeklyAcceptance testing

14.2 Communication Channels

ChannelPurpose
Slack #testingReal-time updates
GitHub IssuesDefect tracking
EmailFormal communications
ConfluenceDocumentation

14.3 Status Reporting

Daily: Test execution progress, blockers Weekly: Metrics dashboard, risk updates Sprint: Summary report, recommendations